March 2008 - End of 2008 Remove debris from the property, cut wild trees and bushes, put a fence around the property.
September 2008 - End of 2008 Conduct archival research necessary for developing architectural blueprints.
October 2008

Complete lab work (test the soil, the building’s foundation, and the wooden beams)

October 2008 - December 2008 Paint the roof support system and replace the roof
January 2009 - March 2009 Develop blueprints by a crew of architects accredited by the Byelorussian government for the renovation of historical property.
March 2009 - August 2009 Indoor renovation phase (bathrooms, walls, floor, doors, ceilings, etc),
September 2009 - July 2010

Install sewer and heater pipes, windows, and electrical wiring

September 2009 - July 2010 Indoor renovation phase (bathrooms, walls, floor, doors, ceilings, etc),